Tuesday, July 10, 2012

Dunwoody Paving Update


Dunwoody Paving Update

=============

From Dunwoody Public Works Department


Dunwoody paving

Upcoming Paving Projects in the City.

This summer, the City is working with three contractor on several paving projects.  One of the contractors, Stewart Brothers, began reconstruction of Leisure Valley Drive in late June and is scheduled to finish Friday, July 13.  Their next stops include: Tennille Court and Arnaud Court followed by the Vernon Oaks neighborhood.
Johnson Landscapes began work on the Mount Vernon bicycle and pedestrian improvements between Ridgeview Road and Ashford Dunwoody Road.  Work will continue on that project into September.
C.W. Matthews will begin resurfacing Ashford Center Parkway on Tuesday, July 9. 
The tentative order of streets for paving this summer includes:
1.       Ashford Center Parkway
2.       Perimeter Center East
3.       Lakesprings Court and Lakesprings Circle
4.       West Fontainbleau Court
5.       Winters Chapel Road
6.       Sanlee Lane and Arrie Way
7.       Charmant Place, Joel Lane, Joel Court and Joel Place
These streets should be completed within 1 month, weather permitting.
Additionally, there will stormwater improvements made to Winters Chapel this week and next week prior to the paving.  Lane closures will occur between the reservoir and Peeler, weekdays between 9:00 a.m. and 4:00 p.m.  Peeler Road and Tilly Mill Road should be used as alternates.

No comments:

Post a Comment