Monday, July 29, 2019

Several Dunwoody crosswalk improvements are about to enter construction phase (Andover / Dunkerrin & Tilly Mill) and (Mt. Vernon & North Peachtree)

http://jkheneghan.com/city/meetings/2019/Jul/Andover_TillyMill_Crosswalk.pdf

Andover / Dunkerrin & Tilly Mill

The crosswalk upgrade at Andover is in the utility relocation phase. Atlanta Gas Light has completed their relocation and we are waiting on Georgia Power to move a couple of poles. They are in the process of getting an easement from one of the property owners and once they have the easement they will relocate the poles on Tilly Mill and our contractor can start work. I anticipate actual construction will likely start in September.   Michael Smith, Public Works

http://jkheneghan.com/city/meetings/2019/Jul/MtVernon_NorthPeachtree_Crosswalk.pdf

Mt. Vernon & North Peachtree

This improvement is slated for the fourth quuarter of 2019.