Dunwoody Paving UpdateFrom Dunwoody Public Works Department |
Upcoming Paving Projects in the City.
This
summer, the City is working with three contractor on several paving
projects. One of the contractors, Stewart Brothers, began
reconstruction of Leisure Valley Drive in late June and is scheduled to
finish Friday, July 13. Their next stops include: Tennille Court and
Arnaud Court followed by the Vernon Oaks neighborhood.
Johnson
Landscapes began work on the Mount Vernon bicycle and pedestrian
improvements between Ridgeview Road and Ashford Dunwoody Road. Work
will continue on that project into September.
C.W. Matthews will begin resurfacing Ashford Center Parkway on Tuesday, July 9.
The tentative order of streets for paving this summer includes:
1. Ashford Center Parkway
2. Perimeter Center East
3. Lakesprings Court and Lakesprings Circle
4. West Fontainbleau Court
5. Winters Chapel Road
6. Sanlee Lane and Arrie Way
7. Charmant Place, Joel Lane, Joel Court and Joel Place
These streets should be completed within 1 month, weather permitting.
Additionally,
there will stormwater improvements made to Winters Chapel this week and
next week prior to the paving. Lane closures will occur between the
reservoir and Peeler, weekdays between 9:00 a.m. and 4:00 p.m. Peeler
Road and Tilly Mill Road should be used as alternates.
|